TM 5-3610-287-24
2-51.
REPAIR LOAD CENTER (CONT)
18.
Feed white ground cable (13) through conduits (11) and (7) and install
with screw (12).
19.
Feed power receptacle cables (8) through conduit (11).
20.
Install cables (8) and power monitor assembly wires (9) with
screws (10).
21.
Feed wires (5) through conduit (7) and install with screws (6).
22.
Install power entry panel cover (4) with screws (3), lockwashers, and
flatwashers.
23.
Install circuit breaker cover panel (2) with screws (1).
WARNING
ELECTRICAL HAZARD. Do not connect power cable to Section
before grounding. Failure to observe this warning may
result in death or serious injury.
24.
Ground Section and connect main power cable.
Test for correct phase and voltage (TM 5-3610-287-10, para 2-6) before
25.
setting MAIN POWER switch to ON.
To test operate, set MAIN POWER switch and MAIN and auxiliary circuit
26.
breakers to ON and ensure lighting and outlets are operational.
Bulb socket
Blackout light system is repaired by replacing: a.
b. Marker light c. Door switch d. Relay
BULB SOCKET
INITIAL SETUP
Tools
Light machine repair tool kit (appendix B, section III, item 11)
Flat-tip screwdriver
Cross-tip screwdriver
Pliers
Materials/Parts
Bulb socket
Wire nut, 2978 (2 required)
2-161