TM 5-6675-319-14
Table 2-1.
OPERATOR PREVENTIVE MAINTENANCE CHECKS AND SERVICES - Cont
B - Before
W - Weekly
AN - Annually
(Number) - Hundreds of Hours
D - During
M - Monthly
S
- Semiannually
A - After
ITEM
NO.
19
IN-
TER-
VAL
S
Q - Quarterly
Bl
- Biennially
ITEM TO BE INSPECTED
PROCEDURE
FILM/PAPER PROCESSOR SYSTEM - Cont
Inspect Flowmeter and Check Flow Rates - Cont
5.
6.
7.
8 .
Turn on PUMP switch and adjust flowmeters
to a reading of 10,40, 70, 100, or 130 as
required, using the center of the flowmeter
f l o a t b a l l s a s r e f e r e n c e p o i n t s .
Insert each tube into the graduated cylinder.
Turn on PUMP switch for 1 minute, then turn
off PUMP switch and measure fluid levels in
graduated cylinders. Record readings for each
setting as shown in sample below.
SAMPLE OF FLOWMETER DATA
ML/MIN
Flowmeter Setting
F i x e r
Developer
10
30
30
40
95
190
70
215
350
100
300
520
130
415
670
Repeat steps 5 and 6 until all flowmeter reading
levels have been completed.
Using data recorded above, plot the actual flow
rates against flowmeter settings. See sample
on the following page:
For Readiness
Reporting,
Equipment Is
Not Ready/
Available If:
2-39