6-6.
OPERATION UNDER USUAL CONDITIONS.
6-6.1 Operating Procedures.
a.
Starting unit.
(1) Move control switch to COLD to start blower motor.
(2) Blower should be allowed to run for 30 seconds to allow unit to stabi-
lize.
Then move control switch to HOT.
This energizes heating element. Hot air
should now be exiting nozzle.
(3) Air
air intake flow
temperature can
control on left
be adjusted by opening
blower housing.
(cooler) or closing (hotter)
Excessive heat
wrap material.
CAUTION
may start fire.
Do not hold heat gun too close to shrink
b. Operating unit.
Direct airflow onto clear film and item to be shrink
wrapped.
Continue only as needed to adequately seal item.
c.
Shutting unit down.
(1)
1 minute to
(2)
Move control switch to COLD.
Allow blower fan to run for approximately
allow heating element to cool down.
Once heating element has cooled, move control switch to off.
6-7. OPERATION UNDER UNUSUAL CONDITIONS. This equipment is designed for operation
only in a controlled environment.
6-8