TM 5-3610-286-20
2-64.
Delivery Pile Lift Motor.
This task covers:
a. Remove
b. Repair
c. Install
d. Adjust
INITIAL SETUP
Tools
Additional Personnel Requirement
17 mm combination wrench
Electrician MOS 35E20
0.050 x 0.375 x 8 in. flat-tip screwdriver
10 mm hex key
General Safety Instructions
Equipment Conditions
WARNING
Suction slowdown assembly must be moved
HEAVY EQUIPMENT. Use care and proper
fully toward delivery end of press
lifting techniques when removing or in-
(para. 2-57)
stalling delivery pile motor. Failure to do
Suction valve assembly removed (para. 2-48)
so may result in serious personal injury.
Electronic control box removed (para. 2-92)
a. Remove. (figure 2-145)
(1) Remove four slotted screws (1) and terminal box and cover (2).
(2) Remove five hex nuts (3) and tag and remove leads (4).
(3) Remove slotted ground screw (5) and ground lead (6).
(4) Support pile lift motor (7) with wooden blocks.
WARNING
Motor exceeds 35 pounds. Use two persons to remove.
(5) Remove hex bolts (8), lockwasher (9), socket-head bolt (10), and Iockwasher (11) from
pile motor mounting plate (12).
(6) Carefully remove pile lift motor (7) through feeder end of press (O/S).
2-324