2-39.
Disengaging Shaft Assembly.
This task covers:
a. Remove
b. Repair
c. Install
INITIAL SETUP
Tools
Equipment Conditions
4 mm pin punch
Form dampening rollers removed
10 mm combination wrench
(TM 5-3610-286-10)
Retaining-ring pliers
Upper guard (O/S) removed (para. 2-18)
Ball-peen hammer
Main guard (D/S) removed (para. 2-20)
Dampening fountain removed (para. 2-37)
a. Remove. (figure 2-78)
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
2-198
Remove two taper pins (1).
Remove two retaining rings (2) and two washers (3).
Slide shaft (4) out through O/S of press frame while grasping and removing both lockout
levers (5) from shaft (4) as it is pulled through the press frame.
Loosen two lock nuts (6) and remove spring rods (7) from rod heads (8).
Remove two lock nuts (6), compression springs (9), washers (10), and guide pieces
(11) from spring rods (7).
Remove spring tension pin (12) and handle (13).
Remove spring tension pin (14) and stud (15).
Remove two tension pins (16) and lever (17).