TM 5-6675-324-14
s.
Remove reed switch RS5 mounting screw and remove reed switch.
Install new reed switch and secure with reed switch mounting screw.
t.
u.
v.
Connect meter leads to reed switch's two pins using clips and
jumper wire.
w.
Move delivering assembly and jam detection lever shaft toward front
of copier to eliminate end play.
x.
Loosen mounting screw of reed switch mounting plate and move reed
switch away from magnet. (Multimeter reading will change from 0 to
infinity.)
Slowly move reed switch closer to magnet, and temporarily tighten
y.
mounting screw so that reed switch is 0.5 mm (0.02 in.) closer to
magnet than when reading changes from infinity to O.
z.
Adjust position of reed switch so that multimeter reading changes
from 0 to infinity when jam detection roller is raised 2.5 mm (0.10
in.) and from infinity to O when jam detection roller is returned to
original position.
aa.
Tighten mounting screw,
ab.
Remove multimeter leads and clips.
Reconnect J6 and J304.
ac.
3-176